Kunshan Plant · Jiangsu  |  Hefei Plant · Anhui, China [email protected]  |  WhatsApp +86 132 6227 6239
C-BOX Electronic Technology Request a Quote

Technical note · 2 November 2026 · Sourcing

19″ subrack MOQ and lead time from China: what actually drives both

Short answer: two suppliers quoting the same 19″ subrack at 15 and 40 days are usually not quoting the same scope. Lead time is set by four things — whether the part is catalogue or new, whether programming and first-article inspection are included, whether finishing is in-house, and whether the batch pays for its own material. MOQ is likewise three different numbers, depending on whether the part is stock-cleared, catalogue or build-to-print. This note sets out both, with the price and MOQ figures we publish per part number.

In this note 1 · What sits inside a quoted lead time 2 · MOQ is three different numbers 3 · Real price and MOQ on four part numbers 4 · Why the cheap 15-day quote exists 5 · What to put in the RFQ 6 · Lead times by scenario

1 · What sits inside a quoted lead time

A 19″ subrack is a Eurocard mechanical assembly — our subrack range is representative — built to IEC 60297-3-100 / -101 at 482.6 mm (EIA-310) mounting width. The metal itself is not the slow part; the sequence around it is. On a build-to-print subrack, the working days are consumed roughly like this:

BlockWorking daysWhat the buyer never sees
Drawing review and process routing2–3Interface check against the rail, guide and panel stack; which operations must precede finishing
Programming and first off2–3Laser / CNC punch programs, bend sequence, weld fixture; the first part is measured, not shipped
Material5–106063 aluminium extrusion is normally stocked; a special cross-section is 2–3 weeks. Steel sheet and stainless are weekly buys
Machining and assembly7–12Cutting, punching, bending, tapping, riveting; insertion of the threaded strips
Finishing5–8Anodising or powder coating — the block most often subcontracted by trading companies, and where their dates slip
Final assembly, FAI, packing2–3Dimensional report and first-article inspection, requested at no extra charge

Added up, a new custom subrack lands around 23–40 working days. That is the honest number, and it is why a catalogue part and a new drawing cannot share a delivery date.

2 · MOQ is three different numbers

“What is your MOQ” has three answers, and they are all true at once:

For a first order, the practical route is a USD 100–300 trial on catalogue parts with no tooling fee, so the interface, the finish and the packing are verified before any volume commitment.

3 · Real price and MOQ on four part numbers

Published figures, EXW Kunshan, for comparison against any quote you are holding. All of them sit inside the 771-part cross-reference, so an existing drawing or an incumbent brand number can be matched directly:

Part numberItemPriceMOQ
34560-584Horizontal rail, rear, type H-ST, heavy, 84 HP, anodisedUSD 3.50 / pc100
34561-384Threaded insert (strip nut), M2.5, for 84 HP railUSD 0.30 / pc1,000
21100-660Sleeve for M2.5, brass, nickel plated (100 pcs pack)USD 0.10 / pc1,000
24560-884Horizontal rail insulation strip, 84 HP, polycarbonateUSD 0.60 / pc1,000

If the job is a shielded assembly rather than a plain cage, the frame parts that close each EMC joint are set out in the companion note on the six contact points in a 19″ subrack.

Two things follow. First, the subrack kit itself — the 24563-133 3 U × 84 HP × 295 mm shielded kit for backplane mounting — is priced on quantity, finish and machining, not on a list price. Second, on small parts the MOQ step matters more than the unit price: an insert at USD 0.30 across 1,000 pcs is USD 300 of material, while the same insert bought as a 20-piece clearance lot costs USD 0.56 each. Whether to buy the small lot or the full box is a project decision, not a supplier preference, and we quote both.

4 · Why the cheap 15-day quote exists

Four mechanisms produce a date the factory cannot hold:

5 · What to put in the RFQ so the lead time is real

Five lines save a week of correspondence:

Asked this way, the answer you get back is a scope, not a wish. We quote within 24 hours on standard items and 3–5 days on custom builds that need a drawing review and process routing, and the lead time is stated on the quotation rather than in the email.

6 · Lead times by scenario

ScenarioTypical lead timeCounted from
Standard catalogue partsabout 10 calendar daysOrder confirmation and deposit
19″ cabinetsabout 21 calendar daysOrder confirmation and deposit
Catalogue part with a modification (holes, cut-outs, silkscreen, colour)the catalogue time plus the finishing and re-inspection steps, stated on the quotationDrawing approval
Build-to-print subrack or chassisquoted per drawing, typically 23–40 working daysDrawing approval and first-article sign-off

Chinese statutory holidays are not counted and extend the delivery date accordingly. Nothing here replaces a quotation: the point is that the number on it can be traced to a block on the table above.

Frequently asked

What is the minimum order quantity for a 19-inch subrack?

Three tiers: stock-cleared items at 10–20 pcs, catalogue parts at 100 or 1,000 pcs as printed on the model page, and build-to-print work from 1 piece with a prototype unit price.

Why is one supplier quoting 15 days and another 40 for the same subrack?

Usually a different scope: stock plus one operation, with finishing subcontracted, versus new programming, own material, controlled finishing and first-article inspection. Ask whether finishing and FAI are inside the date.

Can C-BOX build to our drawing without a tooling charge?

Yes for sheet-metal work — laser, punch, bend and weld are programmed per drawing, so MOQ can be one piece. Tooling charges apply only where a die is genuinely needed (new extrusion profile, die-cast mould), and the tooling belongs to the customer.

Next step. Send the part number or the drawing with the target quantity. We come back with unit price, MOQ, lead time and the process route behind it — and if a cheaper route exists (stock-cleared lot, standard finish, split shipment), we say so in the same reply. Request a quotation.

Need a real MOQ and lead time?

Send the part number or the drawing and the target quantity — we quote the price together with the lead time and say which steps drive it.

Part-number cross-reference Send an RFQ